Next up was doing a materials run to Summit Lumber Co. That required making a stab at materials requirements using some chicken scratches:

Having loaded up the truck with materials and the credit card with a total approaching four digits (lumber ain't cheap these days!), I got started on placing the cement piers and primary support joists.



Then leveraged my hanger nail gun for the second time ever to hang the floor joists:

Next I applied the tongue and groove 3/4" plywood to form the deck. I regretted later not having put some blocking between the joists since it ended up a little spongy after I'd put on the plywood.

 

I dug through our house construction leftovers from 12 years ago and found most of a gallon of Spar Varnish which I applied immediately to the plywood since what would normally be a subfloor is going to be the floor floor.


Put it on before you get it dirty so you get a pretty nice looking surface that is somewhat waterproof. After letting that dry overnight I could use that nice flat surface to pre-assemble the wall units and get them up.




The movie here shows why you want to build the walls laying flat on a good surface so the plane is preserved when you lift it.